The objective of this project is to connect three health centres namely QECH,Ndirande and Limbe with Polytechnic as a hub to Internet using wireless technology.In order to achieve this objective the following tasks are planned:

Activity

Duration

Tools

Personnel

Costs(USD)

Comments

(a)

Testing of pieces of equipment to be used

5 days

Signal Generators, Oscilloscope,

3 Engineers

750

(b)

Configuring radios

5 days

Laptop/PC

3 Engineers

750

(c)

Simulating the network in the lab

8 days

4 Laptops/PCs

4 Engineers

1600

(d)

Installing a repeater at Mpingwe

10 days

Engineering toolbox

3 Engineers

1500

(e)

Installing the station at Polytechnic

8 days

Engineering toolbox

3 Engineers

1200

(f)

Testing the Mpingwe-Poly link

5 days

2 Laptops/PCs

4 Engineers

1000

(g)

Constructing masts for Ndirande,Limbe and QECH

30 days

Work will be Subcontracted.

No masts will be required at Poly and Mpingwe.There is an existing tower at Mpingwe and Poly Building is also sufficient

(h)

Installing the station at Ndirande

8 days

Engineering toolbox

3 Engineers

1200

(i)

Testing Mpingwe-Ndirande link

5 days

2 Laptops/PCs

4 Engineers

1000

(j)

Installing the station at Limbe

8 days

Engineering toolbox

3 Engineers

1200

(k)

Testing Mpingwe-Limbe link

5 days

2 Laptops/PCs

4 Engineers

1000

(l)

Installing the station at QECH

8 days

Engineering toolbox

3 Engineers

1200

(m)

Testing QECH-Poly link

5 days

2 Laptops/PCs

4 Engineers

1000

(n)

Overall testing of the entire network

20 days

5 Laptops/PCs

5 Engineers

5000

(o)

Training of users in all the centres

30 days

3 Laptops/PCs

6 Engineers

9000

Almost all the personnel at the centres are computer illiterate and therefore require some trainning

Notes:

PlanOfAction (last edited 2006-07-06 09:59:09 by TimothyChadza )